Seite 1 - Maintenance

MI/MIHBoilersSeriesGasInstallation,Operation &MaintenanceManual

Seite 2 - TABLE OF CONTENTS

86. Install this boiler so that the gas ignition systemcomponents are protected from water (dripping,spraying, etc.) during appliance operation andser

Seite 3 - USING THIS MANUAL

9C. PIPING FOR ZONED SYSTEMS1. See Figures 3.5 and 3.6 for basic zoned systemlayouts.2. Run each zone pipe down then up to zone toprevent air accumula

Seite 4 - 1. PREINSTALLATION

10D. EXPANSION TANK1. Consult the tank manufacturer’s instructions forspecific information relating to tank installation. Sizethe expansion tank for t

Seite 5 - PREINSTALLATION

11A. INTEGRAL DRAFT HOOD1. The MI/MIH boiler is equipped with a built-in drafthood. This device is designed to:a. provide for the ready escape of flue

Seite 6

12Figure 4.2: Venting with Vent Damper in Vertical PositionFigure 4.3: Venting with Vent Damper in Horizontal PositionC. VENT PIPING AND CHIMNEY1. Ins

Seite 7

D. BOILER REMOVAL FROM COMMONVENTING SYSTEMAt the time of removal of an existing boiler, follow thesesteps with each appliance remaining connected to

Seite 8 - 2. BOILER SET-UP

141. Size and install the gas supply piping properly inorder to provide a supply of gas sufficient to meetthe maximum demand without undue loss ofpres

Seite 9 - 3. WATER PIPING AND CONTROLS

15Table 5.4: Pipe CapacityCapacity of pipe of different diameters and lengths in cubic feetper hour [cubic meter per hour] with a pressure drop of 0.3

Seite 10 - WATER PIPING AND CONTROLS

A. WIRING1. See Figure 6.1 for location of wiring and controls.Use Figures 6.2 and 6.3 to connect the boiler to apower supply and to connect component

Seite 11

17D. SEQUENCE OF OPERATION1. Standing Pilot (See Figure 6.2 above)a. The vent damper is continuously powered. On acall for heat, limit relay R is ener

Seite 12

USING THIS MANUAL 1A. INSTALLATION SEQUENCE . . . . . . . . . . . . .1B. SPECIAL ATTENTION BOXES . . . . . . . . . . . .11. PREINSTALLATION 2A. ACCE

Seite 13 - 4. VENTING

18ELECTRICAL2. Intermittent Ignition (see Figure 6.3 above)a. The vent damper is continuously powered. On acall for heat, limit relay R is energized,

Seite 14 - C. VENT PIPING AND CHIMNEY

19Figure 6.4: Intermittent Ignition System Operating SequenceELECTRICAL

Seite 15 - VENTING SYSTEM

ELECTRICALFigure 6.5: Zone Wiring with Zone ValvesFigure 6.6: Zone Wiring with Circulators20

Seite 16 - 5. GAS PIPING

A. COMPLETING THE INSTALLATION1. Confirm that all water, gas and electricity areturned off.2. Inspect the boiler combustion chamber for foreignobjects

Seite 17 - GAS PIPING

22Figure 7.1: Gas Valve, Manifold and Burner Assembly – Standing Pilot (Continuous Ignition)Figure 7.2: Gas Valve, Manifold and Burner Assembly – Inte

Seite 18 - 6. ELECTRICAL

23START-UP PROCEDURESFigure 7.4: Operating Instructions

Seite 19 - ELECTRICAL

24Figure 7.5: Lighting InstructionsSTART-UP PROCEDURESH24V VR8200/VR8300 9177R If you cannot reach your gas supplier, call the fire department.C

Seite 20

B. CONTROL DESCRIPTIONSSee Figure 6.1 in Section 6 (Electrical) for locations ofthese devices.1. FLAME ROLL-OUT SAFETY SHUT-OFF SWITCH(FLAME ROLL-OUT

Seite 21

26E. CHECKING BURNER INPUT1. Refer to rating label mounted on the jacket top panelto obtain the rated BTU per hour input. In no caseshall the input to

Seite 22

27b. Intermittent Ignition System:i) Turn gas supply off.ii) Set thermostat or controller above roomtemperature to call for heat. Watch for igniterglo

Seite 23 - 7. START-UP PROCEDURES

1A. INSTALLATION SEQUENCEFollow the installation instructions provided in thismanual in the order shown. The order of theseinstructions has been set i

Seite 24 - START-UP PROCEDURES

A. SHUT-DOWN CAUSED BY PILOT OUTAGE, BLOCKED VENT SHUT-OFFSWITCH OR FLAME ROLL-OUT SAFETY SHUT-OFF SWITCHIn the event of a shut-down caused by a pilo

Seite 25

29TROUBLESHOOTINGTable 8.1: Boiler Troubleshooting GuidePROBLEM POSSIBLE CAUSES CORRECTIVE ACTIONS1. No power.2. Limit (Aquastat) not working.3. Flame

Seite 26 - Pilot Burner

30Figure 8.1: Intermittent Ignition System Troubleshooting SequenceTROUBLESHOOTING

Seite 27

31MAINTENANCE9. MAINTENANCEWARNINGProduct Safety InformationRefractory Ceramic Fiber ProductThis appliance contains materials made from refractory cer

Seite 28

A. GENERAL1. Disconnect this boiler from the gas supply pipingduring any pressure testing of the gas system.2. Check pipes adjacent to cold walls or

Seite 29

33E. ANNUALLY (BEFORE START OF HEATINGSEASON)1. Check flueways and burners for cleanliness and cleanif necessary. Use the following procedure if clean

Seite 30 - TROUBLESHOOTING

BOILER DIMENSIONS & RATINGS10. BOILER DIMENSIONS & RATINGSTable 10.2: Series MI/MIH Boiler Ratings1 Net I=B=R water ratings based on an allowa

Seite 31

35REPAIR PARTSREPAIR PARTSSERIES MI/MIH GAS BOILERRepair parts are available from your installer or by contacting PB Heat, LLC, NewBerlinville, PA 195

Seite 32

REPAIR PARTS36Table 11.2: Manifold/Gas Train (MI – Standing Pilot)*For elevations over 2,000 feet above sea level contact PB Heat, LLC.ItemNo.Descript

Seite 33 - 9. MAINTENANCE

*For elevations over 2,000 feet above sea level contact PB Heat, LLC.*For elevations over 2,000 feet above sea level contact PB Heat, LLC.37REPAIR PAR

Seite 34 - MAINTENANCE

2A. ACCESSIBILITY CLEARANCESInstall boiler not less than 24″ (610 mm) between theleft side, top, and front of the boiler and adjacent wall orother app

Seite 35

REPAIR PARTS38Figure 11.4:Block/Draft HoodTable 11.4a: Block/Draft Hood121314Block AssemblyFlue Collector/Draft HoodFlue Collector Blanket SealItemNo.

Seite 36 - Figure 10.1:Boiler Views

39REPAIR PARTSFigure 11.5:JacketTable 11.5: JacketItemNo.DescriptionPart SelectionInformationMI/MIH-03MI/MIH-04MI/MIH-05MI/MIH-06MI-07 MI-08 MI-0916 J

Seite 37 - 11. REPAIR PARTS

REPAIR PARTSTable 11.6: Controls/Circulator/Vent Damper40Figure 11.6:Controls/Circulator/Vent DamperItemNo.DescriptionMI/MIH-03MI/MIH-04MI/MIH-05MI/MI

Seite 38

MI/MIHBoilersSeriesGasInstallation,Operation &MaintenanceManualTO THE INSTALLER:This manual is the property of the owner and mustbe affixed near t

Seite 39

3where:Iother= Input of appliances other than fanassisted in Btu/hrACH = air change per hour (percent of thevolume of the space exchanged perhour, exp

Seite 40

4ii. Where communicating with the outdoorsthrough horizontal ducts, each opening shallhave a minimum free area of 1 in2per 2000Btu/hr (22 cm2per 2000

Seite 41

5c. Each of the appliances served shall beinterlocked to the mechanical air supply toprevent main burner operation when themechanical air supply syste

Seite 42

6BOILER SET-UP1. Provide a sound, level foundation. Locate boiler asnear to the chimney or outside wall as possible andcentralized with respect to the

Seite 43

7A. BOILER SUPPLY AND RETURN1. Size the supply and return to suit the system. Atypical piping arrangement is shown in Figure 3.1.Refer also to the I=B